Surge / rush request
SR-2026-0001
Linked to PO-2026-0012 — Horizon Wave tee — front + back print
Quoted
New ship by May 27, 2026
The ask
Pull-in the PO-2026-0012 ship date by 4 business days to land before Hypland's retail floor reset.
Reason
Hypland confirmed an in-store launch window we need to hit. Customer-driven priority change.
Affected units
4,200
Notice window
9d
Cost items
4
Incremental cost quote
| Category | Item | Amount |
|---|---|---|
| Overtime Premium | OT premium — Saturday shift × 2 | $1,040 |
| Supervision | Floor supervisor weekend coverage | $1,360 |
| Quality | QC inspector — accelerated batch checks | $440 |
| Setup | Re-prioritization setup time | $220 |
| Total incremental cost | $3,060 | |
Notes from Prosper
Estimated. Actuals reconciled in next weekly statement. Pricing per §6.1 — no overtime begins without written approval.
Approve incremental cost?
Per SOP §5, work cannot start until you approve in writing. Approving authorizes Prosper to incur the $3,060 of incremental cost.